# ICRA Breach Response Procedures: Barrier Damage, Airflow Loss, and Dust Migration

**Canonical URL:** https://healthcarefacilityhub.org/icra-breach-response-procedures/
**Parent Topic:** ICRA
**Field Sheet PDF:** https://healthcarefacilityhub.org/wp-content/uploads/2026/11/field-sheet-icra-breach-response-procedures.pdf

## Direct Answer

When an ICRA containment barrier is damaged, negative pressure drops below the ASHE ICRA 2.0 / CDC minimum (-0.01 in. w.g. / -2.5 Pa; many facilities target -0.020 in. w.g.), or dust migrates into adjacent occupied space, dust-generating work must stop immediately per CDC Environmental Infection Control Guidelines. Secure and repair the barrier, restore negative air and HEPA filtration, wet-clean or HEPA-vacuum impacted surfaces (never dry sweep), document the breach and verification readings, and trigger Infection Prevention surveillance or patient relocation when high-risk immunocompromised units are adjacent.

## Core Reference Matrix

| Breach Scenario | Immediate Stop-Work Trigger | First 15-Minute Action | Governing Authority |
| :--- | :--- | :--- | :--- |
| Barrier Damage (torn poly, unsealed penetration, propped door) | Any visible opening or compromised airlock seal | Halt dust-generating work; tape/re-seal poly or close rigid door; inspect corridor | CDC EICG (2003/2019); ASHE ICRA 2.0 |
| Airflow / Pressure Loss (positive or < -0.01 in. w.g.) | Magnehelic/digital monitor drops below -0.01 in. w.g. (-2.5 Pa) or alarm sounds | Stop work; check HEPA NAM power, ducting, filter loading; deploy backup HEPA unit | CDC EICG; ASHE ICRA 2.0; ASHRAE 170 |
| Dust Migration into Clinical / Corridor Space | Visible dust, debris, or tracked footprint outside barrier | Stop work; isolate corridor; wet-wipe and HEPA-vacuum surfaces (no dry sweeping) | CDC EICG (2003/2019) |
| Water Intrusion / Wet Porous Materials | Active leak or wet drywall/ceiling tile inside or adjacent to containment | Shut off/contain source; dry and repair or discard porous materials within 72 hours | CDC EICG (72-hr mold rule) |

## Post-Breach Remediation, Air Verification & Patient-Exposure Checklist

| Phase | Required Verification / Action | Sign-Off Owner |
| :--- | :--- | :--- |
| 1. Containment & Air Quality | [ ] Confirm negative pressure >= -0.01 in. w.g. (-2.5 Pa) and target ACH restored; run diagnostic particle sampling if barrier integrity is questioned (CDC) | Facilities / Contractor Lead |
| 2. Surface Remediation | [ ] Wet-clean and HEPA-vacuum all affected horizontal surfaces, vents, and equipment; replace compromised sticky mats | EVS / Contractor |
| 3. Incident Documentation | [ ] Log breach time, location, ICRA class, root cause, stop-work timestamp, remediation actions, and post-repair pressure reading | Facilities & Safety |
| 4. Patient-Exposure Follow-Up | [ ] Notify Infection Prevention; activate active Aspergillus surveillance for nearby immunocompromised patients (HSCT, transplant, neutropenic); assess relocation if severe | Infection Preventionist |
| 5. Restart Authorization | [ ] Written joint clearance from Infection Prevention and Facilities before resuming dust-generating work | IP + Engineering |

---

*Practitioner prep/reference tool based on CDC Environmental Infection Control Guidelines (2003/2019), ASHE ICRA 2.0 (2022), and ASHRAE 170. Facility Infection Prevention and AHJ policies govern exact site-specific thresholds.*