# Renovation Risk Assessment Planning: Integrated FGI PCRA, ICRA, ILSM, and Security Workflow

**Canonical URL:** https://healthcarefacilityhub.org/renovation-risk-assessment-planning/
**Parent Topic:** FGI
**Field Sheet PDF:** https://healthcarefacilityhub.org/wp-content/uploads/2026/11/field-sheet-renovation-risk-assessment-planning.pdf

## Direct Answer

FGI Guidelines require a multidisciplinary Pre-Construction Risk Assessment (PCRA) before any hospital renovation begins. Rather than running siloed checklists, effective teams execute PCRA as one integrated workflow combining four tracks across every construction phase: (1) ICRA (ASHE ICRA 2.0 dust, barrier, and negative-air controls), (2) ILSM (Joint Commission LS.01.02.01 / NFPA 101 egress, fire watch, and impairment controls), (3) Security & Access Control (worker badging, locked partitions, camera/alarm continuity), and (4) Disaster/Emergency & Utility Resilience (evacuation routes, med-gas/water/power contingencies).

## Core Reference Matrix

| PCRA Track | Core Triggers Evaluated | Required Phased Controls | Governing Authority |
| :--- | :--- | :--- | :--- |
| 1. ICRA (Infection Control) | Demolition, ceiling access, plumbing/water work, adjacent immunocompromised units | ASHE ICRA 2.0 Class I-V barriers, negative air, HEPA, sticky mats, Water ICRA | FGI PCRA; ASHE ICRA 2.0; CDC |
| 2. ILSM (Life Safety) | Blocked exits/corridors, sprinkler/fire-alarm impairment, breached fire/smoke walls | TJC LS.01.02.01: unobstructed egress, fire watch, daily/weekly inspections, training | The Joint Commission; NFPA 101 |
| 3. Security & Access | Exterior envelope breach, contractor traffic in clinical zones, staged equipment | Separate contractor badges, locked construction doors, preserved CCTV/panic alarms | FGI PCRA; Hospital Security |
| 4. Disaster & Utilities | Med-gas/water/power tie-ins, ambulance/evacuation route impacts, noise/vibration | Swing-space phasing, off-hours tie-ins, emergency shutoff & comms tree | FGI PCRA; CMS EP Rule |

## Phased Construction Gate Checklist (Pre-Mobilization -> Phase Transition)

| Gate | Required Multidisciplinary Sign-Off | Sign-Off Team |
| :--- | :--- | :--- |
| Gate 1: Pre-Design PCRA | [ ] Convene Facilities, IP, Safety/Security, Emergency Management & Contractor; document PCRA scope across all phases | Multidisciplinary PCRA Team |
| Gate 2: Pre-Mobilization Permits | [ ] Issue signed ICRA Permit + ILSM Matrix + Utility Shutdown & Security Badging plan before barrier erection | IP + Safety + Facilities |
| Gate 3: Phase-to-Phase Shift | [ ] Build and pressure-verify new airtight phase barrier BEFORE dismantling prior phase barrier; update ILSM egress maps | Contractor + Facilities + IP |
| Gate 4: Daily/Weekly Rounds | [ ] Conduct joint barrier, negative-pressure, egress, fire-watch, and security walkthroughs; log corrective actions | Safety + IP + Engineering |

---

*Practitioner prep/reference tool based on FGI Guidelines PCRA framework, ASHE ICRA 2.0, The Joint Commission LS.01.02.01, and NFPA 101. Confirm all phase permits with facility IP, Safety Officer, and AHJ.*