Direct Answer: Under the FGI Guidelines for Design and Construction of Hospitals, every renovation in an occupied healthcare facility requires a multidisciplinary Pre-Construction Risk Assessment (PCRA) before work begins. Rather than treating infection control, fire safety, security, and emergency management as disconnected forms, effective teams run PCRA as one integrated phased workflow uniting four tracks: (1) ICRA (ASHE ICRA 2.0 barriers, negative air, Water ICRA), (2) ILSM (The Joint Commission LS.01.02.01 / NFPA 101 egress, fire watch, impairment controls), (3) Security & Access Control (badging, locked partitions, CCTV/alarm continuity), and (4) Disaster & Utility Resilience (evacuation routes, med-gas/water/power shutdown contingencies).
Why FGI Mandates a Unified PCRA Before Breaking Ground
In an occupied hospital, a single wall relocation can simultaneously open a ceiling plenum above an ICU (ICRA), narrow an exit corridor (ILSM), disable a badge-reader door (Security), and require a domestic water tie-in (Utility/Disaster). FGI Guidelines mandate a formal PCRA so Facilities, Infection Prevention, Safety/Security, Risk Management, Emergency Preparedness, and the General Contractor resolve conflicts across all four risk tracks before mobilization.
The Four Integrated Tracks of a Hospital PCRA
| PCRA Track | Key Triggers Evaluated | Required Phased Controls | Governing Authority |
|---|---|---|---|
| 1. ICRA (Infection Control) | Demolition, ceiling access, dust/vibration, plumbing tie-ins, adjacent immunocompromised units | ASHE ICRA 2.0 Class I–V barriers, negative air (≥ −0.01 in. w.g.), HEPA filtration, Water ICRA | FGI PCRA; ASHE ICRA 2.0; CDC EICG |
| 2. ILSM (Interim Life Safety) | Blocked/rerouted exits, sprinkler or fire-alarm impairment, breached smoke/fire barriers | TJC LS.01.02.01: free egress paths, fire watch, daily/weekly hazard inspections, worker training | The Joint Commission; NFPA 101 |
| 3. Security & Access Control | Breached exterior envelope, contractor paths near clinical units, staged medical equipment | Distinct contractor badges, locked construction doors, preserved CCTV & panic-alarm coverage | FGI PCRA; Facility Security |
| 4. Disaster & Utility Resilience | Med-gas/water/power shutdowns, EMS/ambulance bay access, noise & vibration | Swing-space sequencing, off-hours tie-ins, emergency shutoff & command-center comms plan | FGI PCRA; CMS EP Rule |
Executing Phased Construction in Occupied Hospitals
Occupied-hospital renovations depend on disciplined phase transitions so containment, egress, and security never drop between phases:
- Swing-Space Sequencing: Relocate clinical operations into completed swing space before demolishing the legacy footprint, running a full PCRA/ICRA/ILSM check on the temporary clinical area as well as the construction zone.
- Micro-Phasing & Off-Hours Tie-Ins: Schedule high-vibration demolition, core drilling, and utility shutdowns (med gas, domestic water, normal/essential power) during off-peak hours with pre-staged backup contingencies.
- Progressive Barrier Overlap: Erect, seal, and pressure-verify the next phase’s airtight containment barrier before dismantling the previous phase’s barrier.
- Continuous Multi-Track Rounds: Conduct documented daily/weekly walkthroughs verifying ICRA negative pressure, ILSM egress/fire-watch logs, locked construction doors, and unblocked evacuation routes.
Four-Gate Phase Sign-Off Workflow
| Project Gate | Required Deliverable / Verification | Sign-Off Owners |
|---|---|---|
| Gate 1: Pre-Design PCRA | Convene multidisciplinary team; map ICRA, ILSM, Security, Hazardous Materials, Noise/Vibration & Disaster impacts for every phase | Facilities, IP, Safety, Security, EM, GC |
| Gate 2: Pre-Mobilization Permits | Issue signed ICRA Permit + ILSM Matrix + Utility Shutdown & Badging Plan prior to barrier erection | IP + Safety Officer + Facilities |
| Gate 3: Phase-to-Phase Transition | Verify new phase containment pressure and updated ILSM egress signage before opening prior phase | GC + Facilities + IP |
| Gate 4: Closeout & Recommissioning | Complete terminal clean, water recommissioning, TAB verification, and restore permanent life-safety systems before ILSM/ICRA closeout | IP + Engineering + Safety |
Related Guides on Healthcare Facility Hub
- FGI Guidelines for Healthcare: 2022 vs 2026 Codes, Room Sizes, and Compliance
- FGI State Adoption Tracker: Which States Adopted the Guidelines, and Which Edition Each One Enforces
- How Do FGI Guidelines Affect Hospital Renovation Projects?
- ICRA Breach Response Procedures: Barrier Damage, Airflow Loss, and Dust Migration
- FGI State Adoption in Practice: How to Pin the Governing Edition Before Design or Procurement
- FGI in Occupied Hospital Renovations: Phased Compliance, Equivalency, and ICRA/ILSM Coordination